Short answer
Prep the slab, dry-lay the pieces, then bond each one with an exterior-rated, polymer-modified thin-set. Thicker or uneven stone gets a mortar bed instead. Grout the joints, let everything cure and seal the stone once it’s dry. Flagstone goes down the same way, so these steps also work for how to put flagstone on top of concrete jobs.
What you’ll need
- Exterior-rated, polymer-modified thin-set, or a mortar mix for thick pieces. Check the bag for the thickness it’s rated for and whether it handles freeze and thaw.
- A notched trowel and a margin trowel
- A rubber mallet, a straightedge and a level
- Plastic joint spacers
- A stiff brush, a degreaser and a hose
- Exterior-rated grout or mortar for the joints
- A wet saw, or an angle grinder with a diamond blade, for cutting
- Eye protection, hearing protection and a respirator rated for stone dust
- A penetrating sealer, if you plan to use one
Cutting slate makes fine dust that can contain crystalline silica. Cut wet where you can, and wear a respirator rated for that kind of dust.
Step 1: Prep the slab
- Sweep and wash the slab. Remove oil, grease, paint or sealer with a degreaser and rinse it off, because adhesive won’t grip well through any of these.
- Fill cracks and chips with a concrete patching product, and let it cure as directed.
- Lightly roughen smooth concrete with a grinder fitted with a cup wheel, or a similar tool, so the adhesive has something to grip. Rinse off the dust.
- Follow the adhesive’s directions on whether the slab should be damp or dry when you bond.
Step 2: Dry-lay the pieces
Lay the slate out without adhesive to plan the pattern, the cuts and the joint widths. Use spacers to keep the joints an even width. Mark the slab’s existing control joints on your layout, and try to line the stone joints up with them, or plan for a membrane. Check the slope with a level as you go. Take a photo or number the pieces so each one goes back in the same place.
Step 3: Mix the adhesive
Mix small batches according to the bag, and use each batch within the working time it lists. Thin-set can skin over or stiffen if it sits too long, and a bond made with stiffened adhesive is more likely to fail.
Step 4: Set each piece
For thin, flat pieces, spread thin-set on the slab with the notched trowel, combing it in one direction. Cover only the area you can set within the open time. For irregular or thick pieces, back-butter each stone, meaning spread adhesive on its back so the contact area is full. Press the piece into place, wiggle it slightly, and tap it down with the mallet. Check it against the straightedge and adjust. Wipe any adhesive off the face of the stone before it sets, using a damp sponge.
Hollow spots are the most common failure. Lift one piece now and then to check that the adhesive covers most of its back. If coverage is partial, pull the piece and redo that spot.
Step 5: Cure and grout
Let the adhesive cure for the time on the bag before you walk on it. Once it has set enough to hold the pieces, pull out the spacers. Press grout or mortar into the joints, then wipe off the residue before it dries. Polymeric sand is made for joints between pavers set on a sand base, so it isn’t usually the choice for mortared stone. Asking what mortar is best for flagstone? Look for an exterior-rated mix that the bag rates for freeze and thaw, and mix it as the label directs.
Step 6: Seal and maintain
Once the grout has cured and the stone is dry, apply a penetrating sealer if you want better stain resistance. Follow the label, and test it on a spare piece first, since sealer can change the color of the stone. Check the joints once a year and fix any loose pieces quickly.
Mistakes that cause trouble
- Bonding over sealer, oil or loose concrete
- Using an indoor-only adhesive outdoors
- Setting thick stone with thin-set alone, which leaves hollow spots that crack under load
- Working in cold, wet or very hot weather outside the adhesive’s range
- Skipping the slope check, so water pools on the surface
- Ignoring a crack that keeps moving