Deck Framing

How to set out a decking frame?

Mark a deck's footprint before digging: check the plan and buried services, square the corners with the 3-4-5 method, and set the post centers and height.

On this page
  1. Check the plan and the site first
  2. Measure from the house wall
  3. Set up stakes, string and batter boards
  4. Square the corners
  5. Mark the post and footing centers
  6. Set the height
  7. Check before you dig
  8. Common mistakes

Setting out means marking the deck’s footprint on the ground before any digging starts: its edges, its corners and the center of every footing. Do it carefully. Every joist and board inherits any error made here, and a frame that starts out of square is hard to correct later.

Check the plan and the site first

Compare your measurements with the plan and, if your area requires one, the permit drawings. Confirm the deck sits inside your property lines. Find buried pipes and cables before you mark or dig; in the US, call 811 first. If the deck attaches to the house, decide where the ledger will sit on the wall.

Measure from the house wall

For an attached deck, the house wall gives your reference line. Walls are often not straight or square, so do not assume the corners are right angles. Measure out from the wall at several points along its length to check it is straight, then take the deck’s measurements from a line you have checked.

Set up stakes, string and batter boards

Drive a stake at each corner and run string between them to show the outline. Batter boards are useful here: fix two boards level across each corner, set back from the dig, and tie the strings to them. Because the batter boards sit back from the excavation, the strings still mark the outline once digging starts.

Square the corners

Check each corner is a right angle with the 3-4-5 method. From the corner, measure 3 feet along one string and 4 feet along the other, and mark both points. If the distance between the marks is exactly 5 feet, the corner is square. If not, adjust one string and measure again. For the reasoning and the larger measurements, see what is the 3/4/5 rule for decking.

Then measure both diagonals across the whole rectangle. When opposite sides match and the diagonals are equal, the rectangle is square.

Mark the post and footing centers

Use the plan to mark the center of each footing on the string lines. Use a plumb bob to drop each point where the strings cross down to the ground, so every footing center sits directly under its planned post position. Mark the ground at each point, then check the marks against the plan before you move on.

Set the height

Decide the height of the deck surface and the top of the beams from the plan. Use a laser level or a water level to carry one reference height from the house wall or a fixed point to each post position, and mark it on the batter boards or stakes. Plan the deck surface to sit below the door threshold, which helps keep water out of the house, and check your local rules for the clearance.

Check before you dig

Recheck the corners, the diagonals and the heights. Measure from the house wall once more, because a small mistake at the start moves every later mark. Once the layout is right, the rest of the frame goes in the order set out in building decking framework.

Common mistakes

  • Measuring from the outside edge of a post instead of its center.
  • Using an out-of-square house wall as the only reference.
  • Setting the strings too close to the dig, so they get knocked out during excavation.
  • Skipping the diagonal check on a large deck.

The complete guide to deck framing

Building a Decking Framework Step by Step