Leveling the ground is the step people most often rush, and it is the hardest to fix once the base is down. The goal is a flat, firm, well-drained surface that is square and at the right height. The steps below cover a gravel base, which suits many small sheds. A concrete slab adds forms, reinforcement and pouring steps, which are a separate job.
Check for utilities first
Before you dig, find out what runs underground. In the US, call 811, the “call before you dig” service, so the utility lines can be marked. In other countries, contact your local utility-locating service or the utility companies directly. Overhead power lines matter too when you are handling long boards or tall equipment, so keep clear of them.
Mark and square the footprint
- Mark the corners of the shed footprint with stakes and string. Leave a little room around the shed for access and drainage.
- Check that the corners are square with the 3-4-5 method. From one corner, measure 3 feet along one string and 4 feet along the other. When the corner is square, the distance between those two marks is 5 feet. For a larger shed, use multiples such as 6, 8 and 10 feet, or 9, 12 and 15 feet.
- Measure both diagonals of the rectangle. If they match, the corners are square.
Remove sod, roots and topsoil
Strip the sod and topsoil from the footprint, along with roots and any other organic material. These break down and settle over time, which can tilt a shed or leave the floor uneven. Set the removed topsoil aside if you want to use it for landscaping elsewhere.
Set a level reference
Pick a method you can read accurately:
- A line level hung on a tight string, for short distances
- A laser level, which projects a level line across the site
- A water level, which is a clear hose filled with water, with each end held at a mark. The water sits at the same height at both ends, so you can compare heights across the site.
Set a reference height, usually at or near the highest corner of the site. Then measure how far each other corner sits below it. Those differences tell you how much soil to cut or fill.
Cut high spots and fill low spots
Cut down the high spots and remove the soil. For low spots, add fill in thin layers rather than one thick dump, and compact each layer before you add the next. Avoid soft or organic material, such as leaves, sod or old roots, as fill, since it will settle.
Add and compact a gravel base
Many small sheds sit on a layer of compacted crushed stone or gravel, often around 4 inches (about 10 cm) deep. The right depth depends on your soil and the shed, so check the shed maker’s instructions and local practice. Crushed stone drains better than sand or loose soil, which helps keep water away from the floor.
Spread the stone in layers, and compact each one with a plate compactor or a hand tamper. Keep the surface even.
Lay a straight board across the surface, called a screed, with a level on top to find high and low spots. Fill or scrape where needed, then compact again. Slope the finished surface slightly away from the shed, so water runs off rather than pooling under it.
Check the level and square again
Once the base is compacted, check the surface again with a long level and the diagonals. Small differences can be taken up with shims at the bottom frame. Larger ones should be fixed in the base before the shed goes on.
Other base options
If you would rather use concrete, the steps are covered in laying concrete foundation for shed. Pavers are another option, and the layers for a pavers shed base differ from gravel.
Time spent on the site pays off. A level, square and well-drained base keeps the walls straight, the doors closing and the roof doing its job.