Concrete Shed Bases

Laying a Concrete Foundation for a Shed

How to lay a concrete slab for a shed, from checking local rules and digging out the site to the gravel base, forms, pouring, finishing and curing.

On this page
  1. Check the rules and the utilities first
  2. Decide whether a slab is the right base
  3. Size the slab and pick the spot
  4. Clear the site and plan the height
  5. Build and level the gravel base
  6. Set up the forms
  7. Add reinforcement
  8. Mix or order the concrete
  9. Pour, screed and finish
  10. Cure the slab
  11. Anchor the shed to the slab
  12. Common mistakes to avoid
  13. Looking after the slab

Check the rules and the utilities first

A concrete slab is one of the most durable bases for a shed, but it is a permanent job, so sort out the paperwork and the ground before you dig. Many areas require a permit for a shed above a certain size, and some require one for any structure. Ask your local building department before you buy materials. Also check setback rules, which limit how close a building can sit to a property line, and any homeowners association rules or easements that cross the site.

Before you dig, call your local utility locating service. In the United States, calling 811 starts a free check that marks buried gas, electric, water and phone lines. Hitting a buried line can be dangerous and costly.

Decide whether a slab is the right base

A slab is not the only way to support a shed. Readers often ask “Do I need a cement foundation for a shed?” The answer depends on the shed’s size and weight, the soil and local rules. Other common bases include a compacted gravel pad, treated timber laid on gravel, concrete blocks or piers, and pavers. If you would rather avoid concrete, a pavers shed base is one alternative, and much of the preparation below still applies.

A slab costs more and takes more work, but it gives a hard, level floor that stays off damp soil. It suits heavier sheds and workshops well. A simpler base may be enough for a small garden shed. If you bought a shed kit, read the maker’s instructions, since some makers specify the base they require.

Size the slab and pick the spot

Measure the shed’s footprint, then make the slab a few inches larger on each side so every wall sits fully on concrete. For many sheds, a slab about 4 inches thick is a common starting point. Readers often ask “How thick should a concrete base be for a shed?” The answer depends on how heavy the shed will be and how it will be used.

Choose a spot with good drainage, away from downspouts and low areas where water collects. Leave room to bring in materials and to move a wheelbarrow or mixer. Mark the corners with stakes and string, then check that the corners are square by measuring both diagonals. If the two measurements match, the corners are square.

Clear the site and plan the height

Remove grass, roots and topsoil from the slab area. Topsoil contains organic matter that breaks down over time, which can let the slab settle unevenly.

Decide the finished height first. Many people set the top of the slab a few inches above the surrounding ground to help keep rainwater out. Then dig down about 8 inches below that height, enough for a 4-inch gravel base and a 4-inch slab.

Build and level the gravel base

Spread crushed stone, often sold as 3/4-inch crushed gravel or road base, in layers of a few inches at a time. Compact each layer with a plate compactor or a hand tamper. The compacted gravel gives the slab a stable, well-drained base, and that is the main reason to use it.

When the gravel is compacted to about 4 inches, screed it flat with a straight board and check it with a level. The slab can only be as level as the base under it. A related question is “Can I pour concrete straight onto soil?” The short answer is usually no, because soil can shift, settle and hold moisture. Gravel is the usual answer.

Set up the forms

Build the frame from straight, untwisted lumber set on edge. For a 4-inch slab, 2x6s are a common choice, since they are deep enough to hold the concrete. Set the top edges at the finished height. Drive stakes outside the boards every few feet and fasten the boards to them. Check each top edge with a level and a string line, and check the corners with the diagonal measurement again.

Slope the finished slab slightly away from the shed walls so water runs off instead of pooling at the door. A common guide is a fall of about 1/8 inch per foot, and you can set it while you check the forms.

Add reinforcement

Lay a grid of rebar or welded wire mesh over the gravel, raised on plastic or concrete chairs so it sits in the upper half of the slab. Mesh that lies on the gravel ends up at the bottom of the slab, where it does little. Reinforcement helps hold cracks tight, but it does not stop cracks from forming.

Some builders also lay a plastic sheet over the gravel to slow moisture rising from the ground. It is optional for most sheds.

Mix or order the concrete

Work out the volume first: length times width times thickness, with the thickness in feet. A 10 by 10 foot slab that is 4 inches thick holds about 33 cubic feet. Add a little extra for waste and uneven spots.

For a small slab, bagged premixed concrete is often the simplest choice. Mixing from separate cement, sand and gravel is possible, and a 4-2-1 ratio is a common rule of thumb, but it is harder to keep consistent. For larger slabs, a truck of ready-mix may be faster and cheaper. Many suppliers charge a minimum order and a delivery fee, so ask for a quote.

Wear waterproof gloves, long sleeves and eye protection when you handle wet concrete. It is alkaline, and long contact can burn skin. Add water gradually. Too much water weakens the finished slab, so follow the bag’s guidance and aim for a mix that holds its shape on a shovel.

Pour, screed and finish

Pour in one session if you can, starting at the far end and working toward the entrance. Use a shovel or rake to push the concrete into the corners and against the forms.

Screed the surface by pulling a straight board across the top of the forms with a back-and-forth sawing motion. This levels the concrete and fills low spots. Then smooth it with a bull float, a wide, long-handled float.

Wait until the sheen of bleed water on the surface has gone before you trowel or broom the top. Finishing too early traps water near the surface and weakens it.

Cut control joints with a groover or a saw to about a quarter of the slab’s depth, which is roughly 1 inch for a 4-inch slab. Joints give cracks a planned place to form, so they are less likely to run in random lines.

Cure the slab

Curing keeps the concrete moist long enough to gain strength. Keep the surface damp, or cover it with plastic sheeting, for several days. Many guides suggest about seven days. Protect the slab from heavy rain, from hot sun and drying wind, and from freezing. Fresh concrete that freezes can lose strength permanently. Concrete reaches its full design strength over about 28 days.

Wait at least several days before you set the shed on the slab or stack heavy loads on it.

Anchor the shed to the slab

In windy areas, a shed should be fixed to its base. Anchors can be bolts set into the wet concrete or anchors installed in the cured slab. Follow the shed maker’s instructions and any local wind requirements for the number and type of anchors.

Common mistakes to avoid

  • Pouring onto topsoil, or skipping the gravel base
  • Leaving the forms or the gravel out of level or out of square
  • Adding too much water to make the mix easier to pour
  • Pouring in freezing weather or skipping curing
  • Setting the shed down before the slab has cured

Looking after the slab

Hairline cracks are common in concrete and are often cosmetic. A crack that widens, or a slab that sinks or tilts, usually points to a problem with the base or the drainage, and a professional should look at it. Sealing the surface can reduce staining and water soaking in.