Laying a flagstone patio with concrete means setting each stone in a bed of mortar or stiff concrete, on top of a compacted base. It takes more care than a sand-set patio, but the result is stable. The order of work is: plan, dig, build the base, make the bed, set the stones, fill the joints and cure the patio.
Before you dig
Check for buried utilities before any digging. In the United States, call 811 a few days ahead. Check with your local building office about permits, setbacks and property lines.
Mark the outline with stakes and string. Check the layout against the house, the doors and the way the yard drains.
Gather your tools: a spade and rake, a plate compactor (which you can rent), a level and a straight board, a string line, a rubber mallet, a mason’s trowel, a wheelbarrow, a mixing tub, and a wet saw or masonry chisel for cuts.
Excavating and building the base
Dig to the total depth the job needs: the stone thickness, the bed and the base. As an example, 1.5-inch stone on a 1.5-inch bed over a 4-inch base needs about 7 inches of total depth.
Spread the crushed stone in layers of roughly 2 inches, and compact each one fully before adding the next. Build the fall into the base, about 1/8 to 1/4 inch per foot away from the house. Set a rigid edge around the perimeter so the bed and stone cannot spread. Check the finished base with a level and a straight board, and fix any soft or low spots now rather than later.
Making the mortar or concrete bed
There are two common setups.
On a new base, spread a stiff mortar or concrete mix about 1 to 2 inches thick, and screed it flat. Dampen the base lightly before placing the bed, so it does not draw water out of the mix. Mix in small batches that you can place within the working time on the bag, so the mix does not stiffen before the stones go down.
On an existing concrete slab, the question is whether the slab is sound and drains properly. Many people ask: can flagstone go on top of concrete? Often, yes, if the slab is in good condition. Remove sealer, oil and loose material, and clean the surface well. Use a bonding agent or bonding mortar as the label directs. Check the slope first, because on a fixed slab you can correct it only by making the bed thicker on one side. The steps for how to put flagstone on top of concrete are similar to a new bed, but the slab sets the starting level.
Ask your supplier what mortar is best for flagstone in your area, since products and climate both matter.
Setting the stones
Dry-fit the pieces on the bed before you commit to mortar. That lets you choose shapes that give even joints and place the cuts near the edges. Start at a straight reference line, such as a string or a straight board, and work across the area in small sections.
Press each stone into the bed, then tap it with a rubber mallet until it is level and firmly bedded. Some installers also spread a thin layer on the underside of each piece for better contact. Check the level and the fall as you go. Wipe mortar off the face of each stone with a damp sponge right away, because dried mortar can stain natural stone.
Filling the joints and curing
When the bed is firm enough to hold the stones without moving, pack the joints with mortar, pressing it in and finishing it a little below the surface of the stone. Tool the joints smooth if you want a neat finish. Learning how to mortar between flagstones takes practice, so try a test section before you do the whole patio.
Cure the patio slowly. Keep the mortar damp for several days by misting it or covering it with damp burlap. Avoid plastic sheeting that can mark the surface. Hot, dry or windy weather dries the mortar too fast and can crack it. Keep foot traffic light for several days, and keep heavy items and furniture off for longer. Protect the fresh work from rain and freezing.
When the patio has cured, you can seal it if you choose. Follow the sealer label for timing.
Safety and weather
- Wet concrete and mortar are caustic. Wear gloves, long sleeves and eye protection, and rinse any splashes at once.
- Cutting stone makes fine silica dust. Wet the stone and the blade, and wear a respirator rated for silica.
- Lift heavy pieces with a cart or a helper, and keep your back straight.
- Avoid placing mortar or concrete near freezing temperatures, or ahead of heavy rain.
These steps are general guidance. Check your product labels and local codes before you start.