The short answer
A 10 by 10 foot slab that is 4 inches thick needs about 33 cubic feet of concrete. With 80-pound bags, which yield about 0.6 cubic feet each, that comes to about 56 bags before waste. Order a few extra. Unused bags are often returned if they are unopened, but running short partway through a pour is much harder to fix.
Work out the volume
Multiply length by width by thickness, with every measurement in feet:
- Length: 10 feet
- Width: 10 feet
- Thickness: 4 inches, which is 4 divided by 12, or about 0.33 feet
- 10 × 10 × 0.33 = about 33 cubic feet
Concrete is often quoted by the cubic yard, and there are 27 cubic feet in a cubic yard. So this slab needs about 1.2 cubic yards.
How many bags you need
Each bag’s yield is printed on the label. The figures below are common yields, but check the label of the brand you buy:
- 80-pound bag, about 0.6 cubic feet each: about 56 bags
- 60-pound bag, about 0.45 cubic feet each: about 74 bags
- 40-pound bag, about 0.3 cubic feet each: about 111 bags
Allow for waste
Add 5 to 10 percent for spills, uneven ground and small mistakes in the forms. For the 80-pound example, adding 10 percent gives about 62 bags. That is about 4,960 pounds of material, and each bag is heavy to carry, so a wheelbarrow or a helper makes the job easier.
Bags or ready-mix?
For a slab this size, bags are a common choice. A truck of ready-mix can be faster for bigger pours, but many suppliers have minimum orders and delivery charges, and the truck needs clear access to the site. Costs grow with area, so readers often ask “How much would a 20x20 concrete slab cost?” when they plan a bigger pour.
Thickness changes everything
The bag count depends mostly on thickness. Four inches is a common starting point for a shed slab, and heavier use may call for more. Readers often ask “How thick should a concrete base be for a shed?” The difference is large. A 5-inch slab over the same 10 by 10 area needs about 42 cubic feet, or roughly 70 bags of 80-pound mix.
Don’t forget the gravel
The gravel base takes its own calculation. A 4-inch gravel base under the same footprint is also about 33 cubic feet of compacted material. Loose gravel packs down when you compact it, so order a bit more than the calculated figure.
A quick check
Multiply the area by the thickness in feet, divide by the bag yield, and round up. Ordering a little extra costs less than running short partway through a pour.